Heat network registration with Ofgem: who must register by January 2027
Updated
Operators and suppliers of a district, communal, self-supply, industrial or shared ground loop heat network in GB must register with Ofgem by 26 January 2027. The service is open now.
Question 1
Where is the heat network?
The regimes diverged on 27 January 2026. Great Britain moved to Ofgem authorisation; Northern Ireland stayed on the 2014 metering and billing regulations.
Email me this result
We will send you these figures and a link back to them. One email, nothing else unless you tick the box.
Do you have to register your heat network with Ofgem?
Ofgem calls the networks in scope 'relevant heat networks'. Operators and suppliers "must identify the operator and supplier for any of your relevant heat networks and register the networks with us by 26 January 2027". Source: Ofgem: who should register.
Its registration guidance gives 27 January 2027 as the end of the first part of the initial period (registration guidance, para 3.7). Ofgem's own pages say the 26th, so plan to that. In scope:
- District networks: heating, cooling or hot water to 2 or more buildings.
- Communal networks: one building divided into separate premises.
- Self-supply networks: an organisation heating only itself, such as a hospital, a campus or a prison. One that also supplies a third party registers as district or communal instead.
- Industrial networks: heat mainly for an industrial process at one or more industrial sites.
- Shared ground loop networks: a shared closed ground or water loop feeding each customer's own heat pump.
- Self-supply, industrial and shared ground loop networks register too, but carry fewer obligations.
Networks that are out of scope
- A single house in multiple occupation heated by a shared system.
- A building converted into several dwellings with one energy source of no more than 45kWth.
- A single building with shared facilities that is not divided into separate premises, such as a care home.
- A third-party waste heat producer that neither operates nor supplies.
- A communal network that only heats or cools through air conditioning and supplies no hot water (Ofgem).
Operator, supplier or both
The operator controls the transfer of heat on the network and the material assets it needs, even where contractors run it day to day.
The supplier holds the customer contracts, billing, complaints and consumer protection duties. One organisation can be both (Ofgem). The operator starts the registration and invites the supplier, who needs its own account before it can be invited (Ofgem: how to prepare).
What registration asks for
- A regulatory contact, usually the most senior person responsible for heat networks, who requests access and signs in with GOV.UK One Login using an individual work email, never a shared mailbox.
- The organisation's details, and a fit and proper declaration for everyone with significant managerial responsibility or influence over the heat networks.
- For each network, the sections that apply to it: introductory information, the energy centre, customers and metering, consumer protections, billing and other suppliers.
- No documents: Ofgem says it will not ask you to upload supporting documents or evidence, and declaring that you are not yet compliant does not stop you registering (Ofgem: how to prepare; guidance, para 3.2).
Where the service stands (read 28 October 2026)
- The digital service is open for registration and still called a private beta, "fully functional" with data stored securely. Ofgem replies to an access request within 10 working days (Ofgem: comply with heat networks consumer protection regulations).
- A registration pause applies to an organisation that operates and supplies a district network where at least one building contains a communal network it alone operates and supplies: it should create an account but not register those networks until Ofgem updates it (Ofgem).
What follows the date
- Operating or supplying a relevant heat network without authorisation is an offence under regulation 14 of the 2025 market framework regulations. Activity begun on or before 26 January 2027 is authorised automatically, which Ofgem calls deemed authorisation (Ofgem consultation, 5 October 2026).
- A network that starts operating or supplying from 27 January 2027 must apply to Ofgem for authorisation first. Ofgem proposes a short application before the activity starts, registration within 3 months of starting, and no fee; the consultation closes on 2 November 2026 (Ofgem).
- A network that started between 1 April 2025 and 26 January 2027 is deemed authorised only until 26 January 2028. Ofgem proposes to grant it authorisation from its registration information with no further assessment, so registering is how such a network carries on past that date (Ofgem).
- After registering, operators and suppliers report data to Ofgem every quarter and year: see Ofgem heat network reporting, and for the rules that come with authorisation, heat network authorisation.
Ofgem takes questions on the roles and the service at heatnetworksregulation@ofgem.gov.uk, published on its who should register page.